Slobozia ecological waste deposit completed by Klarwin as general contractor in 7 months
CASE STUDY

Slobozia ecological waste deposit completed by Klarwin as general contractor in 7 months

8 August 2025

16,831 sqm waterproofed surface, 235,000 m³ total storage volume and advanced leachate collection systems — delivered on time and to high standards.

At Klarwin, we deliver major projects with precision and environmental responsibility.

For Vivani, we completed as general contractor the waste deposit in Slobozia, built in just 7 months (January 20 – July 29, 2025): 16,831 sqm waterproofed surface, 235,000 m³ total storage volume, Naue Group geomembrane – 9,653 sqm smooth and 7,178 sqm textured, Airwell Group (Australia) pneumatic systems for leachate pumping.

A project built for safety, efficiency and environmental protection, delivered on time and to high standards.